Jul 18, 2017 Research papers

How would you crash the project (which activities would you crash) to keep the project on schedule and achieve the original duration, if Activity B actually takes 5 weeks instead of the planned 3 weeks?

This paper concentrates on the primary theme of How would you crash the project (which activities would you crash) to keep the project on schedule and achieve the original duration, if Activity B actually takes 5 weeks instead of the planned 3 weeks? in which you have to explain and evaluate its intricate aspects in detail. In addition to this, this paper has been reviewed and purchased by most of the students hence; it has been rated 4.8 points on the scale of 5 points. Besides, the price of this paper starts from £ 40. For more details and full access to the paper, please refer to the site.

Scheduling and Project Management: Pert and CPM

INSTRUCTIONS:

Case Analysis

At the Hard Rock Cafe, like many organizations, project management is a key planning tool. With Hard Rock`s constant growth in hotels and cafes, remodeling of existing cafes, scheduling for Hard Rock Live concert and event venues, and planning the annual Rockfest, managers rely on project management techniques and software to maintain schedule and budget performance.

"Without Microsoft Project," says Hard Rock Vice-President Chris Tomasso, "there is no way to keep so many people on the same page." Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within a tight 9-month planning horizon. As the event approaches, Tomasso devotes greater energy to its activities. For the first 3 months, Tomasso updates his MS Project charts monthly. Then at the 6-month mark, he updates his progress weekly. At the 9- month mark, he checks and corrects his schedule twice a week.

Early in the project management process, Tomasso identifies 10 major tasks (called level 2 activities in a work breakdown structure, or WBS):talent booking, ticketing, marketing/PR, online promotion, television, show production, travel, sponsorships, operations, and merchandising. Using a WBS, each of these is further divided into a series of subtasks. The following table identifies 26 of the major activities and subactivities, their immediate predecessors, and time estimates. Tomasso enters all of these into the MS Project software. Tomasso alters the MS Project document and the time line as the project progresses. "It`s okay to change it as long as you keep on track," he states.

Activity Description Predecessor Normal Time (weeks) Normal Cost Crash Time (weeks) Crash Cost

A Finalize site and building contracts --- 7 $7,500 4 $11,500

B Select local printer A 3 $500 2 $800

C Hire production manager A 3 $1,200 2 $1,700

D Design promotional Web site B 5 $6,000 3 $9,000

E Set TV deal D 6 $4,000 4 $6,500

F Hire director E 4 $1,200 3 $1,700

G Plan for TV camera placement F 2 $500 2 $500

H Target headline entertainers B 4 $2,000 3 $3,500

I Target support entertainers H 4 $2,000 3 $3,500

J Travel accommodations for talent I 10 $9,000 7 $16,000

K Set venue capacity C 2 $300 1 $400

L Ticketmaster contract D 3 $1,400 2 $1,900

M On-site ticketing L 8 $7,000 6 $11,000

N Sound and staging C 6 $9,000 5 $12,000

O Passes and stage credentials G 7 $4,000 5 $5,800

P Travel accommodations for staff B 20 $15,000 15 $23,000

Q Hire sponsor coordinator B 4 $600 3 $800

R Finalize sponsors Q 4 $1,000 3 $1,400

S Define/place signage for sponsors R 3 $3,000 2 $4,200

T Hire operations manager A 4 $1,200 2 $1,800

U Develop site plan T 6 $6,000 5 $8,500

V Hire security director T 7 $1,500 5 $3,000

W Set police/fire security plan V 4 $1,000 3 $1,600

X Power, plumbing, AC, toilet services U 8 $4,000 6 $7,000

Y Secure merchandise deals B 6 $6,000 3 $7,500

Z Online merchandise sales Y 6 $5,000 4 $7,500

The day of the rock concert itself is not the end of the project planning. "It`s nothing but surprises. A band not being able to get to the venue because of traffic jams is a surprise, but an `anticipated` surprise. We had a helicopter on stand-by ready to fly the band in," says Tomasso.

On completion of Rockfest in July, Tomasso and his team have a 3-month reprieve before starting the project planning process again.

Source: Professor Barry Render, Jay Heizer and Beverly Amer.

Case Assignment

Please turn in a paper of one to two pages (page counting does not include cover and reference list) discussing the following questions:

1. Identify the critical path and its activities for Rockfest. How long does the project take (what is the duration time)?

2. How would you crash the project (which activities would you crash) to keep the project on schedule and achieve the original duration, if Activity B actually takes 5 weeks instead of the planned 3 weeks? (Explain your logic)?

Hints: You are welcome to take a look at ppt presentation#2 in the background material. Starting from slide #13, you will see an example of how to find critical path and how to crash a project. You are welcome to download a 60-day trial version of MS Project (optional). However, detailed explanations of your rationale and calculations are still expected.

Assignment Expectations

1. Answer questions with clarity.

2. Show depth and breadth in your paper to enhance the quality of your paper.

3. Try your best to search in our library to find some papers/articles to support your argument and show them in the reference list.

4. Identify some major challenges a project manager faces in events such as this one..

CONTENT:

Pert and CPM Name: Institution: Introduction Project management is a key planning tool at the Hard Rock Cafe, as is true of many organizations. With Hard Rock`s constant growth, remodeling of existing hotels and cafes, Hard Rock Live concert scheduling for event venues, and annual Rockfest planning, managers rely on project management techniques and MS Project software to schedule, budget and maintain performance. "Without Microsoft Project, there is no way to keep so many people on the same page." says Hard Rock Vice-President Chris Tomasso. Rockfest event is attended

...

0% Plagiarism Guaranteed & Custom Written, Tailored to your instructions


International House, 12 Constance Street, London, United Kingdom,
E16 2DQ

UK Registered Company # 11483120


100% Pass Guarantee

Order Now

STILL NOT CONVINCED?

We've produced some samples of what you can expect from our Academic Writing Service - these are created by our writers to show you the kind of high-quality work you'll receive. Take a look for yourself!

View Our Samples

corona virus stop
FLAT 25% OFF ON EVERY ORDER.Use "FLAT25" as your promo code during checkout