How much extra capacity can he get without causing anotheroperation to become the bottleneck?

This paper concentrates on the primary theme of How much extra capacity can he get without causing anotheroperation to become the bottleneck? in which you have to explain and evaluate its intricate aspects in detail. In addition to this, this paper has been reviewed and purchased by most of the students hence; it has been rated 4.8 points on the scale of 5 points. Besides, the price of this paper starts from £ 45. For more details and full access to the paper, please refer to the site.

Beck Manufacturing and Plant Capacity

Read the “Beck Manufacturing” case study in Chapter 8 of your text. In a three- to four-page paper, address the following:

  • Calculate the capacity of each machine center and the capacity of the system.
  • Analyze where the focus of the company’s efforts should be if Beck wants to expand capacity. Determine how much extra capacity he can get without causing another operation to become the bottleneck.
  • Suggest ways Beck can expand capacity without purchasing new equipment.

Your paper should be in paragraph form (avoid the use of bullet points) and supported with the concepts outlined in your text and additional scholarly sources.

Submit your three- to four-page paper (not including the title and reference pages). Your paper must be formatted according to APA style as outlined in the Ashford Writing Center and must cite at least three scholarly sources in addition to the textbook.

Beck Manufacturing

AlBeck, president ofBeck manufacturing, wants to determine the capacity of his facility, which produces steering gears for auto manufacturers.He has asked you to sort through the data and determine the capacity of the system and how that capacity may be increased. The operation isa product layout that produces large numbers of nearly identical products. The process includes milling, grinding, boring, drilling, andassembling, in that order. Each finished product requires one operation on each type of machine. For example, each finished part is processedon one of the five milling machines, one of the seven grinding machines, etc.

The facility runs two 8hour shifts per day, with a third shift for maintenance. The industrial engineering department has provided you with thefollowing data on present operations. In addition, you have been told that assembly operations, while not unlimited, can be easily changed tomeet the need.

Operation

Number of Machines

Run Time per Piece (min.)

% Reject Rate

Milling

5

2

3

Grinding

7

3

5

Boring

3

1

2

Drilling

6

2.5

7

  1. Calculate the capacity of each machine center and the capacity of the system.
  2. IfBeck wants to expand capacity, where should he focus the company’s efforts? How much extra capacity can he get without causing anotheroperation to become the bottleneck?
  3. How may Mr.Beck expand capacity without purchasing new equipment? Be specific.

0% Plagiarism Guaranteed & Custom Written, Tailored to your instructions


International House, 12 Constance Street, London, United Kingdom,
E16 2DQ

UK Registered Company # 11483120


100% Pass Guarantee

Order Now

STILL NOT CONVINCED?

We've produced some samples of what you can expect from our Academic Writing Service - these are created by our writers to show you the kind of high-quality work you'll receive. Take a look for yourself!

View Our Samples

corona virus stop
FLAT 25% OFF ON EVERY ORDER.Use "FLAT25" as your promo code during checkout